Contract Information
| Project Name | THOMPSON FALLS-WEST & THOMPSON FALLS-EAST |
| Advertise Date | 03/01/2018 04:00 PM |
| Close Date | 03/26/2018 10:00 AM |
| Let Date | 03/29/2018 09:00 AM |
Notifications
No notifications found for this contract
Addendums
No addendums found for this contract
Clarifications
-1-
Submitted: Tuesday 20-MAR-2018 09:34 AM
The U.S. Department of Labor (USDOL) issued General Decision Number MT 180080 for Highway Construction Projects effective March 2, 2018. There were numerous increases to the various worker classification wage rates and fringes amounts. In addition, USDOL issued another General Decision Number MT 180080 dated March 16, 2018 to correct an error. The city of Helena was added to the Travel Pay Zone locations for the Electrician Classification in General Decision MT 180080 dated March 16, 2018. The Federal Wage Rates found in Section II or III of the bid package proposal are hereby replaced with the attached: FEDERAL WAGE RATES
|
Questions
|
-1-
Submitted: Wednesday 21-MAR-2018 10:22 PM
Company: LHC, Inc.
Contact: David Steely
Regarding SP 25, Cold Millings disposal, is the contractor responsible for stockpiling the millings at the Sanders County location or the MDT Maintenance yard, or will this be handled by others.
Answer
Submitted: Monday 26-MAR-2018 08:21 AM
Haul and stockpile millings to the locations specified in the special provision.
|