Skip to main content

Contract Information


Project Name MULTI-USE PATH-SE PABLO
Advertise Date 03/15/2018 04:00 PM
Close Date 04/09/2018 10:00 AM
Let Date 04/12/2018 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

-1-
Submitted: Tuesday    20-MAR-2018 09:29 AM  
The U.S. Department of Labor (USDOL) issued General Decision Number MT 180080 for Highway Construction Projects effective March 2, 2018.  There were numerous increases to the various worker classification wage rates and fringes amounts.  In addition, USDOL issued another General Decision Number MT 180080 dated March 16, 2018 to correct an error.  The city of Helena was added to the Travel Pay Zone locations for the Electrician Classification in General Decision MT 180080 dated March 16, 2018.   The Federal Wage Rates found in Section II or III of the bid package proposal are hereby replaced with the attached:
  FEDERAL WAGE RATES

Questions

-1-
Submitted: Friday    30-MAR-2018 02:31 PM  
Company: Mission Valley Concrete D.B.A. Harding Civil Construction  
Contact: Trenton Harding  
What is the warranty period for this project? Is there a performance and payment bond of 100%?
Answer
Submitted: Wednesday    04-APR-2018 01:08 PM
There are no project-specific warranties on this project.
The amount of the Performance Bond required is 100% of the amount bid.