|
-3-
Submitted: Tuesday 07-AUG-2018 04:44 PM
Company: Century Companies, Inc.
Contact: Estimating
Can MDT provide the approximate number of locations for mid-block sidewalk/approach replacement, mid-block curb and gutter replacement, and mid-block sidewalk replacement. Quantities for said mid-block improvements were provided, however, determining work efforts necessary for items such as survey, design, subsurface utility investigation, environmental consideration, right of way certification sidewalk and approach construction agreements (from each adjacent landowner), and mobilization are all dependent upon the number of locations.
Answer
Submitted: Thursday 08-AUG-2018 04:48 PM
Refer to Attachment M of the RFP. There is a General Summary for each community that gives the quantity for developing the bid price proposal.
Big Timber: The existing alley approach locations to be replaced (5) are shown for P-91. We anticipate the number of additional mid-block sidewalk replacement locations to range between 15 and 20. A few of these mid-block sidewalk locations will also be associated with approaches (other than the 5 alley). We anticipate the number of mid-block curb and gutter replacement locations to be less than five, with a few of these also being associated with approaches. The C & G replacement areas all correspond with sidewalk or approaches.
Roundup: We anticipate the mid-block sidewalk replacement locations to range between 15 and 20. Only a couple of these are associated with approaches. The majority of additional sidewalk replacement areas occur on Main Street.
Hardin: We anticipate the mid-block sidewalk replacement locations to range between 10 and 15. Only a couple of these are associated with approaches. The majority of additional sidewalk replacement areas occur on Center Avenue.
It will be up to the selected DB Firm to work with the MDT EPM and MDT staff to further define the locations for mid-block sidewalk and approach work.
|