-1-
Submitted: Friday 18-MAY-2018 02:15 PM
Company: SK Geotechnical
Contact: Cory Rice
If a pile redrive is required, what will be the required waiting period?
Answer
Submitted: Wednesday 23-MAY-2018 09:14 AM
A minimum of 72 hours.
|
|
-2-
Submitted: Monday 21-MAY-2018 02:57 PM
Company: Diamond Drilling and Sawing
Contact: Eric Blackburn
Please post the asbuilt drawings of the bridges scheduled for replacement.
Answer
Submitted: Thursday 24-MAY-2018 11:00 AM
The files linked below represent the as-built drawings for the structures. MDT provides them for informational purposes only. They do not include drawings for modifications to the structures, such as joint replacements and guardrail revisions and may not completely represent current conditions. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents.
The files can be found at the following link: AS-BUILT DRAWINGS
|
|
-3-
Submitted: Tuesday 22-MAY-2018 11:49 AM
Company: Inventure Civil
Contact: Ed Austin
Section 58 MSE Retaining Wall Specification - are inextensible reinforcements (galvanized steel) acceptable for use on this project?
Answer
Submitted: Wednesday 23-MAY-2018 04:12 PM
The design and specifications of the MSE elements is up to the MSE engineer hired by the contractor subject to the minimum requirements of the State and based on the geotechnical report.
|
|
-4-
Submitted: Wednesday 23-MAY-2018 11:40 AM
Company: SLETTEN CONSTRUTION
Contact: TRACY GILBERT
37. Temporary Shoring, states that basis of payment is to include all costs in bid item Lump Sum bid for Temporary Shoring, which I did not find that in the bid items. Will there be an addendum issued with that bid item?
Answer
Submitted: Thursday 31-MAY-2018 02:55 PM
Revised Answer: Tuesday 12-JUN-2018 12:44 PM
The bid item for Temporary Shoring will be added by addenda. The revised plan sheet B2 can be found at the following link:
NEWLY REVISED PLAN SHEET B2
|
|
-5-
Submitted: Thursday 24-MAY-2018 09:46 AM
Company: Sletten Construction
Contact: Tracy Gilbert
Can you please confirm that the shop plans for the resin (fiberglass) scuppers do not need to have an engineers stamp on them.
Answer
Submitted: Tuesday 29-MAY-2018 12:12 PM
No, the item would not require an engineer's stamp as it is a manufactured part. The shop plan would need to confirm that it is load rated.
|
|
-6-
Submitted: Thursday 24-MAY-2018 03:47 PM
Company: Riverside Contracting Inc.
Contact: Estimating
I do not see any specification detailing what you want for Special Borrow. This material is not within a sub-excavation situation but is specified as part of the Typical Sections. Please specify.
Answer
Submitted: Tuesday 29-MAY-2018 01:32 PM
Provide Special Borrow material that meets a soil classification of A-1-a(0) with an R-value greater than 30. The special borrow is also to be free of organic and other deleterious material and have 100 percent by weight passing the 6-inch sieve and a maximum of 8 percent by weight passing the number 200 sieve.
|
|
-7-
Submitted: Thursday 24-MAY-2018 03:55 PM
Company: Riverside Contracting Inc.
Contact: Estimating
Special Provision No. 33 call for this project to be a class one ride. I don't think with the length of this project the ride should even be considered. All the paving work is chopped up runs with multiple set backs. I think MDT should eliminate the ride on this project. We request it be deleted.
Answer
Submitted: Tuesday 05-JUN-2018 11:31 AM
Category 1 Ride is required for the Interstate mainline and Ramps only.
|
|
-8-
Submitted: Thursday 24-MAY-2018 04:00 PM
Company: Riverside Contracting Inc.
Contact: Estimating
Plan sheets for the construction of the cross-overs shows a Typical with the cross-over being chip sealed however, the delineated approximate quantity sheet doesn't list the chips and CRS2P. Please specify the chip seal needs done or does not to be done. The Plant Mix also is not specified as to size and the oil to grade so please specify what size aggregates and what oil grade you want the cross -overs paved with.
Answer
Submitted: Monday 04-MAY-2018 11:13 AM
Chip seal all crossovers.
West End Ramp Crossover STA 380+07 to STA 387+14 EB/WB
Cover – 13,400 SY
Seal – 670 GAL
East End Ramp Crossover STA 413+43 to STA 428+05 EB/WB
Cover – 12,100 SY
Seal – 605 GAL
West End Crossover STA 288+36 to STA 296+40 EB/WB
Cover – 11,700 SY
Seal – 585 GAL
East End Crossover STA 502+26 to STA 510+30 EB/WB
Cover – 11,700 SY
Seal – 585 GAL
Pave all crossovers with Grade S 3/4" PMS and PG 64-28 AC.
|
|
-9-
Submitted: Friday 25-MAY-2018 07:01 AM
Company: Inventure Civil
Contact: Ed Austin
The specification for MSE panel color 58-D.5.a.4 on page 49 - is this color to be applied after wall construction or is the color required to be integral to the concrete mix?
Answer
Submitted: Tuesday 29-MAY-2018 09:10 AM
Any of the concrete specified to be colored is intended to be integral to the mix, and not applied afterwards.
|
|
-10-
Submitted: Tuesday 29-MAY-2018 09:11 AM
Company: Contech Engineered Solutions
Contact: Dennis Dirks
Would PVC pipe meeting the MDT standard spec 708.05.4 be allowed as an option to RCP on the storm sewer? We installed this pipeexperimentally on Tatro Street many years ago for a previous MDT project.
Answer
Submitted: Tuesday 29-MAY-2018 01:11 PM
No, use concrete as per plans.
|
|
-11-
Submitted: Tuesday 29-MAY-2018 03:46 PM
Company: Riverside Contracting Inc.
Contact: Dennis Devous
1) Can you provide the amount of Embankment per cross over & slip ramp for all stations listed.
2) Please check the locations as it seems if the stationing is correct the cross-over is 11446 feet on one set & 6665 Feet on the other & if it is that long I think your plant mix calculation is incorrect. Please check all the quantities.
Answer
Submitted: Monday 04-MAY-2018 11:15 AM
West End Ramp Crossover STA 380+07 to STA 387+14 EB/WB
Embankment – 1760 CY
East End Ramp Crossover STA 413+43 to STA 428+05 EB/WB
Embankment – 2200 CY
West End Crossover STA 288+36 to STA 296+40 EB/WB
Embankment – 1920 CY
East End Crossover STA 502+26 to STA 510+30 EB/WB
Embankment – 1920 CY
|
|
-12-
Submitted: Monday 04-JUN-2018 10:01 AM
Company: Tensar
Contact: Gary Sander
Is there a link to the full geotechnical report for the project?
Answer
Submitted: Monday 04-JUN-2018 11:10 AM
Attached are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.); alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.). The documents can be found at: GEOTECH REPORT
Revised Answer
Submitted: Monday 04-JUN-2018 12:45 PM
There are two additional reports in the GEOTECH REPORT link noted above.
|
|
-13-
Submitted: Tuesday 05-JUN-2018 01:02 PM
Company: Riverside Contracting Inc.
Contact: Estimating
We typically chip at .40 to .42 gal/sy so please check your gallons of Emulsified chip oil as well as let us know which oil your using, CRS2 or CRS2P?
Answer
Submitted: Wednesday 06-JUN-2018 01:45 PM
Use CRS 2P.
West End Ramp Crossover STA 380+07 to STA 387+14 EB/WB
Cover - 13,400 SY
Seal - 23.9 tons
East End Ramp Crossover STA 413+43 to STA 428+05 EB/WB
Cover - 12,100 SY
Seal - 21.6 tons
West End Crossover STA 288+36 to STA 296+40 EB/WB
Cover - 11,700 SY
Seal - 20.9 tons
East End Crossover STA 502+26 to STA 510+30 EB/WB
Cover - 11,700 SY
Seal - 20.9 tons
Revised Answer
Submitted: Tuesday 12-JUN-2018 02:37 PM
Use CRS-2P.
West End Ramp Crossover STA 380+07 to STA 387+14 EB/WB
Cover 2314 sq. yds.
Seal 4.1 tons
East End Ramp Crossover STA 413+43 to STA 428+05 EB/WB
Cover 3365 sq. yds.
Seal 6.0 tons
West End Crossover STA 288+36 to STA 296+40 EB/WB
Cover 2517 sq. yds.
Seal 4.5 tons
East End Crossover STA 502+26 to STA 510+30 EB/WB
Cover 2517 sq. yds.
Seal 4.5 tons
|
|
-14-
Submitted: Wednesday 06-JUN-2018 08:40 AM
Company: Century Companies, Inc.
Contact: Estimating
Can the 4.5" Special Design pin down curb be cast in place?
Answer
Submitted: Friday 08-JUN-2018 01:35 PM
We take no exception to using a cast-in-place curb as long as the curb is secured with pins.
|
|
-15-
Submitted: Wednesday 06-JUN-2018 10:14 AM
Company: Century Companies, Inc.
Contact: Estimating
Would it be permissible to build the bridges during the winter? This could result in savings to the Department.
Answer
Submitted: Friday 08-JUN-2018 02:55 PM
Updated: Tuesday 12-JUN-2018 03:32 PM
Bridge construction during winter shutdown will be allowed. See Clarification No. 1 for revisions to Special Provision No. 21 – SEQUENCE OF OPERATIONS and Special Provision No. 22 – TRAFFIC CONTROL.
Special Provision #22 – Traffic Control – paragraph 1) k) is hereby deleted.
|
|
-16-
Submitted: Thursday 07-JUN-2018 07:09 AM
Company: White Resources Group, Inc.
Contact: estimating
Sheet 72 PCCP Joint Layout - STA 66+56 to 66+93 - Is there to be reinforcement under the median island? Please provide the reinforcement and joint layout for the median island.
Sheet 77 PCCP Joint Layout - STA 73+20 to 73+59 - Is there to be reinforcement under the median island? Please provide the reinforcement and joint layout for the median island.
Steel Street - Is there to be reinforcement under the median island? Please provide the reinforcement and joint layout for the median island.
Steel Street - Are the longitudinal joints on the Steel St legs to be Transverse contraction joints as drawn?
Answer
Submitted: Tuesday 12-JUN-2018 11:08 AM
There is no reinforcement under the median island on plan sheet 72, 77, and Steel Street. See detail Sheet 70 Median Cap. Joint layouts for the concrete median caps will be established in the field. See Special Provision No. 55 for jointing requirements.
The longitudinal lane joints on Sheet 77 should be longitudinal contraction joints.
|
|
-17-
Submitted: Thursday 07-JUN-2018 07:25 AM
Company: Century Companies, Inc.
Contact: Estimating
Is the crushed aggregate course under the sidewalks included in the bid item for crushed aggregate course or is it incidental to the sidewalk on this project?
Answer
Submitted: Friday 08-JUN-2018 01:39 PM
See Standard Specification 608.04. The crushed aggregate course is incidental to the sidewalk.
|
|
-18-
Submitted: Thursday 07-JUN-2018 07:34 AM
Company: Century Companies, Inc.
Contact: Estimating
Is the crushed aggregate course material under the 4" and 6" median caps included in the bid item for crushed aggregate course or is it incidental to the median caps?
Answer
Submitted: Friday 08-JUN-2018 01:41 PM
See sheet 71 detail. The crushed aggregate course is incidental to the median.
|
|
-19-
Submitted: Thursday 07-JUN-2018 08:21 AM
Company: Riverside Contracting, Inc.
Contact: Estimating
There appears to be some confusion with the quantities listed in the plans for the crossovers. Sheet 113 & 114 each have a summary box for the estimated quantities for the same entrance ramp (four summary boxes for two locations). This would be doubling up the materials. Sheet 115 & 116 also have summary boxes(4) for the same median crossovers(2) which would double up these quantities as well. The stationing listed on these sheets is also wrong. Please issue new sheets with the proper estimated quantities (Including Emb) and stationing to avoid the possibility of doubling the costs to do the work.
Answer
Submitted: Monday 11-JUN-2018 03:37 PM
The informational quantities are published in duplicate on the corresponding plan sheets for the crossovers and should not be double counted. There is an error for the informational quantities for the crossovers and the following quantities should be used for your information.
West End Ramp Crossover STA 380+07 to STA 387+14 EB/WB
Plant Mix Surfacing 595 tons
Asphalt Cement 36.9 tons
Crushed Aggregate Course 771 cubic yards
Emulsified Asphalt Tack 116 gals
24” Drain w/racets 530 feet
East End Ramp Crossover STA 413+43 to STA 428+05 EB/WB
Plant Mix Surfacing 865 tons
Asphalt Cement 53.6 tons
Crushed Aggregate Course 1,112 cubic yards
Emulsified Asphalt Tack 168 gals
24” Drain w/racets 800 feet
West End Crossover STA 288+36 to STA 296+40 EB/WB
Plant Mix Surfacing 647 tons
Asphalt Cement 40.1 tons
Crushed Aggregate Course 839 cubic yards
Emulsified Asphalt Tack 126 gals
Cable Guardrail 240.8 feet
24” Drain w/racets 580 feet
East End Crossover STA 502+26 to STA 510+30 EB/WB
Plant Mix Surfacing 647 tons
Asphalt Cement 40.1 tons
Crushed Aggregate Course 839 cubic yards
Emulsified Asphalt Tack 126 gals
Cable Guardrail 240.8 feet
24” Drain w/racets 580 feet
The stationing shown on the details is intentionally broad to indicate the range in which field staff can locate the crossovers. The stationing does not represent the begin / end stations for construction of the crossovers. Construct the crossovers at the locations directed by the Project Manager.
Detail design mapping does not exist at the locations of the crossovers and estimated embankment quantities have been calculated based on assumed field conditions. Contractors should make their own assessment regarding costs to be included in the bid price for the crossovers.
|
|
-20-
Submitted: Thursday 07-JUN-2018 03:45 PM
Company: Malcolm Drilling
Contact: Adam Hosterman
Will the soil nail wall aesthetic treatment (Section 60.A.7.a) need to be carved as well as including color pigment?
Answer
Submitted: Monday 11-JUN-2018 03:34 PM
The aesthetic treatment consists of a surficial stain application only.
|
|
-21-
Submitted: Thursday 07-JUN-2018 03:44 PM
Company: TrueNorth Steel
Contact: Juel Berg
Please clarify if the grate detail on sheet 63 is for reference on the trash guards listed in the bid items. If not, please add drawing details for the trash guards required on this project.
Answer
Submitted: Tuesday 12-JUN-2018 09:16AM
The attached detail depicts the 18” RCP FET Trash Guards. At the 12” C900 with FETS, use a 12” RCP FETS and field connect the concrete to C900 pipe and use the attached detail. This detail is for informational purposes only. DETAIL OF TRASHGUARD RCP
|
|
-22-
Submitted: Friday 08-JUN-2018 11:14 AM
Company: MWHC
Contact: Chris Connors
Special provision 21 and the plan pages 115 and 116 require cable rail to be placed across the crossovers that are to remain in place. No specifics are given as to what type is required. The drawings however appear to look like the cable rail shown in the MDOT drawings. In every project that i am aware of, there has been a requirement to use the NCHRP 350 median cable rail to close crossovers. Which is to be bid on this project?
Answer
Submitted: Tuesday 12-JUN-2018 03:45 PM
Install high tension cable rail systems and terminal sections on the specified cross-overs when ramps are no longer needed for the construction of the project. The cable rail and terminal sections need to be NCHRP 350 approved and installed per the manufacturers drawings. Install cable rail where it won't be in conflict with drainage structures. Include the cost of the cable rail and terminal sections in the lump sum bid crossover-const, maintain, close.
|
|
-23-
Submitted: Friday 08-JUN-2018 01:43 PM
Company: Doeden Construction
Contact: Eric Doeden
The integral colors: Red-brown brick and Ochre don't seems to be any concrete colors the manufactures can easily produce. Can you please specify desired colors that the manufacturers have in their portfolios in order to create a known and proven product and keep the prices reasonable.
Answer
Submitted: Tuesday 12-JUN-2018 02:34 PM
Provide earth tone colors as approved by the Project Manager.
|
|
-24-
Submitted: Friday 08-JUN-2018 02:11 PM
Company: Quality Landscape Seeding, Inc.
Contact: Estimating
The Invitation for Bids includes item number 610-100-103 (Seeding Area No 3) and item number 610-100-327 (Fertilizing Area No 2). On the proposal and plan sheet, it doesn't include these items. The proposal and plan sheets also includes 97 SQYD of item number 610-100-490 (Turf Reinf Mat-Natural Fiber). Please clarify which items are up for bid.
Answer
Submitted: Monday 11-JUN-2018 11:00 AM
The Invitation for Bid document was prepared a day prior to advertisement of the contract. Last minute changes to quantities relating to revegetation were made immediately prior to advertising. The quantities listed in the Bid Package Proposal Schedule of Items match the plans and Seeding Special Provision. The AASHTOWare™ Project Bids bid file is also correct. Bid the items as shown in the Bid Package Proposal and bid file.
|
|
-25-
Submitted: Friday 08-JUN-2018 03:04 PM
Company: Century Companies, Inc
Contact: Estimating
Are the quantities listed in the Additional Grading Summary included in the Grading Summary, and if not, how are these quantities paid for?
Answer
Submitted: Monday 11-JUN-2018 03:15 PM
The quantities are included in the Grading Summary.
|
|
-26-
Submitted: Friday 08-JUN-2018 03:13 PM
Company: Century Companies, Inc.
Contact: Estimating
Will the chip & seal deadline of Sept 1st be extended so that the cross-over's can be completed this construction season or will MDOT allow the cross-overs to be utilized next spring until a chip & seal can be placed on them after the June 1st (chip seal) start date?
Answer
Submitted: Monday 11-JUN-2018 03:30 PM
There should be sufficient contract time to complete the cross-overs prior to the deadline. In the event there isn't enough time beyond the contractor's control the deadline will be extended as weather permits.
|
|
-27-
Submitted: Friday 08-JUN-2018 03:26 PM
Company: Century Companies, Inc.
Contact: Estimating
Under Special Provision #21 (Sequence of Operations), please clarify - "B.1) maintaining one lane of two-way traffic along South Haynes Avenue". Can we to Interpret this as "one lane of traffic" alternating in each direction with a maximum wait time for the traveling public of 15 minutes? Please verify.
Answer
Submitted: Monday 11-JUN-2018 07:53 AM
Maintain two way traffic on Haynes Avenue during construction at all times unless approved by the Project Manager. Short duration closures of 15 minutes or less are allowed without prior approval. Closures lasting longer than 15 minutes require coordination with and approval from the Project Manager.
|
|
-28-
Submitted: Sunday 10-JUN-2018 06:21 PM
Company: White Resources Group, Inc.
Contact: estimating
Sheet 70 - Curb and Roundabout Detail - Special Design Pin Down Median Curb - Drive Over (Concrete Paving) 1. Where is the pin down curb located?
Answer
Submitted: Monday 11-JUN-2018 03:18 PM
See Sheet 100 for the location of the Special Design Pin Down Median Curb.
|
|
-29-
Submitted: Monday 11-JUN-2018 09:32 AM
Company: Sletten Construction
Contact: Chad Mares
After doing a quantity takeoff of the Concrete-Class Structure bid item, we come up with about 398 CY's instead of MDT's quantity of 298.3 CY's. Please verify the correct quantity for Concrete-Class Structure so it can be bid accordingly.
Answer
Submitted: Tuesday 12-JUN-2018 08:55 AM
Revised Answer: Tuesday 12-JUN-2018 12:45 PM
The quantity of Concrete-Class Structure will be revised to 400.5 cubic yards by addenda.
Revised Plan Sheet B2 can be found at the following link: REVISED PLAN SHEET B2
|
|
-30-
Submitted: Monday 11-JUN-2018 11:25 AM
Company: Montana Lines, Inc.
Contact: Trevor Livesay, PE
Please clarify Bid Item 617 781 000, Remove and Salvage Misc Electrical.
Answer
Submitted: Tuesday 12-JUN-2018 10:25 AM
Remove and salvage the existing luminaires in accordance with Standard Specification 617.03.22. The luminaires will become the property of the contractor.
|