Project Name EAST HOLLY STREET-SIDNEY & SIDNEY-URBAN (UPP)
Advertise Date 06/14/2018 04:00 PM
Close Date 07/09/2018 10:00 AM
Let Date 07/12/2018 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

-1-
Submitted: Tuesday    10-JUL-2018 02:40 PM
Place classes Deck and Overlay-SF concrete with a temperature between 50 and 80 °F (10 and 26 °C). Place all other classes of concrete with a temperature between 50 and 85 °F (10 and 29 °C).

Questions

-1-
Submitted: Friday    06-JUL-2018 12:55 PM  
Company: Contech Engineered Solutions  
Contact: Dennis Dirks  
Would MDT consider a VE proposal for use of F949 pipe in lieu of the RCP?
Answer
Submitted: Monday    09-JUL-2018 09:46 AM
No, complete the extension of the exiting concrete storm drain system with concrete pipe, per plans.