Project Name 3 M SE WHITEFISH-BR DECK
Advertise Date 06/14/2018 04:00 PM
Close Date 07/09/2018 10:00 AM
Let Date 07/12/2018 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

-1-
Submitted: Tuesday    10-JUL-2018 02:41 PM
Place classes Deck and Overlay-SF concrete with a temperature between 50 and 80 °F (10 and 26 °C). Place all other classes of concrete with a temperature between 50 and 85 °F (10 and 29 °C).

Questions

-1-
Submitted: Wednesday 27-JUN-2018 10:04 AM
Company: Cutting Edge Excavation, LLC
Contact: Marc Blanden
Are all of the costs associated with the digout excavation incidental to the unit price for Item 301 020 453 Non-Frost Susceptible Backfill?

Answer
Submitted: Thursday 28-JUN-2018 08:40 AM
Yes.

-2-
Submitted: Friday    29-JUN-2018 04:26 PM
Company: Schellinger Construction Company
Contact: Estimating
For some reason the grading & sub-excavation on this project is and is intended to be bid as "incidental" to other items. Leaving the excavation as incidental will skew the unit pricing of other items and will complicate any potential changes. Will MDT add a bid item for excavation?
Answer
Submitted: Friday    06-JUL-2018 08:35 AM
All excavation is incidental to the Non-Frost Susceptible Backfill bid item and will not be measured separately. An excavation bid item will not be added.

-3-
Submitted: Monday    09-JUL-2018 09:25 AM
Company: Schellinger Construction Company, Inc.
Contact: Estimating
With the Sub Ex, Backfill, Gravel, Paving and Guardrail operations needing to take place with the two phase construction of the bridge deck the 60 working days seems insufficient. Would MDT please add additional 20 Working Days?
Answer
Submitted: Tuesday 10-JUL-2018 08:17 AM
No, a modification to the contract time will not be made.