Contract Information
| Project Name | SF 159 RESERVE ST BARRIER RAIL |
| Advertise Date | 07/12/2018 04:00 PM |
| Close Date | 08/06/2018 10:00 AM |
| Let Date | 08/09/2018 09:00 AM |
Notifications
No notifications found for this contract
Addendums
|
-1-
Submitted: Thursday 02-AUG-2018 01:00 PM
An Addendum has been posted for this project: ADDENDUM
To download the addendum bid files, click here: BID FILES
|
-2-
Submitted: Tuesday 07-AUG-2018 01:47 PM
A 2nd Addendum has been posted for this project: ADDENDUM NO. 2
To download the addendum bid files, click here: BID FILES
|
Clarifications
|
-1-
Submitted: Wednesday 18-JUL-2018 02:37 PM
Plan Sheets 2 and S1 are hereby replaced. REVISED SHEETS 2 & S1
An addendum will be issued to delete Items:
620 011 315 STRIPING-WHITE TAPE 4 IN QUANTITY 2,416.00 LNFT
620 011 317 STRIPING-BLACK TAPE 1 1/2 IN QUANTITY 4,831.00 LNFT
And replace with Item:
620 011 319 STRIPING-CONTRAST TAPE 7 IN QUANTITY 2,416.00 LNFT
The formal addendum will tentatively be issued on August 2, 2018.
|
-2-
Submitted: Tuesday 24-JUL-2018 08:40 AM
Place classes Deck and Overlay-SF concrete with a temperature between 50 and 80 °F (10 and 26 °C). Place all other classes of concrete with a temperature between 50 and 85 °F (10 and 29 °C).
|
Questions
|
-1-
Submitted: Friday 03-AUG-2018 09:03 AM
Company: L & J Construction Group LLC
Contact: Estimating
Would MDT consider adding 20 more contract days to the project? With this project being night work and fines for not having road open by 7AM, the production of Class A and Overlay will be decreased significantly per shift.
Answer
Submitted: Monday 06-AUG-2018 09:21 AM
Contract Time will be increased by an additional 5 Working Days. An addendum will be issued revising Special Provision No. 2, CONTRACT TIME to 25 Working Days.
|