Contract Information


Project Name HELENA-WEST
Advertise Date 09/27/2018 04:00 PM
Close Date 10/22/2018 10:00 AM
Let Date 10/25/2018 09:00 AM

Notifications

No notifications found for this contract

Addendums

-1-
Submitted: Thursday 18-OCT-18 08:57 AM
An Addendum has been posted for this project:  ADDENDUM
To download the addendum bid files, click here:  BID FILES
-2-
Submitted: Wednesday 24-OCT-18 11:38 AM
An Addendum has been posted for this project:  ADDENDUM 2
To download the addendum bid files, click here:  BID FILES

Clarifications

-1-
Submitted: Friday 28-SEP-2018 03:39 PM
The linked special provision, Polymer Overlay, is hereby made part of this contract.  POLYMER OVERLAY

Questions

-1-
Submitted: Tuesday   02-OCT-2018 12:23 PM  
Company: PMS  
Contact: Kris Woll  
According to special provisions 23, it states prevent millings from entering aquatic resources. There is aquatic resources the entire distance of the project according to the specials, does this mean the chips will have to be pickup broomed on the entire project or can we sweep them on to the shoulders without entering the aquatic area.
Answer
Submitted: Friday   05-OCT-2018 11:08 AM
Please review Special Provision 23 - Protection of Aquatic Resources-Millings and Chips - as to the requirements for disposal of millings and the approximate locations identified as apparent aquatic resources within the project limits.   Coordinate with the Project Manager to employ appropriate methods to avoid placement of materials in these areas and other areas which may be identified within the project limits.

-2-
Submitted: Tuesday   02-OCT-2018 04:24 PM  
Company: Alpine Sign, Inc  
Contact: John  
There are two stations in the Signs Schedule calling for Type XI reflective sheeting on D series Ground Mount Increment signs. Stations 35+920 Rt and 36+149 LT D8-2a. My understanding of the new sheeting requirements would have these built using Type IV as are the other green background Increment signs on this project. Please clarify.
Answer
Submitted: Friday   05-OCT-2018 11:04 AM  
The corrected plans sheets S1 and S4 can be found at the following link:
  REVISED PLAN SHEETS S1 & S4 
The revisions to the quantities for bid items - Signs-Alum Sheet Increment Sheeting (XI) and Signs-Alum Sheet Increment Sheeting (VI) will be made by addenda.
Revised Answer
Submitted: Monday 22-OCT-2018 11:15 AM
See answer to Question No. 9 for further information.

-3-
Submitted: Friday    12-OCT-2018 10:39 AM
Company: Schellinger Construction Company, Inc.
Contact: Estimating
With no construction activities allowed in Bald Eagle Protection area from February 1 - June 15 and Cold Milling, HIR, Plant Mix Surfacing and Bridge Repair activities need to take place in this area at the start of contract time. Will MDT please move the Contract Time - Flex Time NTP date to June 17, 2019?
Answer
Submitted: Wednesday 17-OCT-2018 01:25 PM
Special Provision No. 2, CONTRACT TIME – FLEX TIME PROCEED DATE, Paragraph B is hereby revised:

B. Notice to Proceed.  The notice to proceed will be issued with an effective date of June 17, 2019.  The Contractor may change the notice to proceed date to an earlier date if written notification is received at least ten calendar days in advance of the date selected and the selected date is approved by the Project Manager.  Include an updated schedule with the notification.

-4-
Submitted: Tuesday   16-OCT-2018 09:16 AM
Company: Schellinger Construction Company, Inc.
Contact: Estimating
Will MDT please provide a Cold Milling Detail for the connections at Ten Mile Creek Bridge, Beginning of Project and End of Project. It appears three of these locations will need to be milled 0.32' depth. Cold Milling Summary shows 0.15' depth for all Cold Milling. Please clarify.
Answer
Submitted: Wednesday 17-OCT-2018 10:57 AM
Typical Section No. 4 on Sheet 5 and the Cold Milling Summary Frame on Sheet 7 have been revised and are hereby made part of this contract.  The cold milling depth at the bridge ends is changed.  The bid quantity of COLD MILLING - 8,137.00 SQYD remains unchanged.

REVISED PLAN SHEETS 5 AND 7

-5-
Submitted: Tuesday   16-OCT-2018 11:15 AM
Company: Schellinger Construction Company, Inc.
Contact: Estimating
Typical Section NO. 2 on sheet 4 shows the center turn lane section contains Thermoplastic. Does the Thermoplastic need to be removed prior to HIR operations? If yes will MDT please add a bid item for Thermoplastic Removal.
Answer
Submitted: Wednesday 17-OCT-2018 12:49 PM
Removal of thermoplastic striping is not required by MDT.  If removal of thermoplastic striping is deemed necessary by the contractor, include the cost of removal in the bid price of Hot Recycled Plant Mix.

-6-
Submitted: Tuesday   16-OCT-2018 12:39 PM
Company: Schellinger Construction Company
Contact: Estimating
Can MDT provide some clarity as to why Hot In Place Recycle is being utilized on this project? The specifications basically "sole source" the work - limiting it to only 1 or 2 OUT-OF-STATE contractors who have the equipment and intend on quoting the work. The mobilization costs alone for the equipment to complete the HIR work will probably be astronomical and with only 1 or possibly 2 HIR bidders, what is in place to keep the pricing in check?

There should be plenty of contractors interested in rehab-ing this stretch of road using proven & cost effective conventional methods.

Looking at the Future Projects forecast, there appears to be a limited amount of plant mix coming out and Montana has plenty of IN-STATE contractors looking for work for next season.
Answer
Submitted: Thursday 18-OCT-2018 08:37 AM
MDT investigated several methods for rehabilitating this section of roadway. The existing plant mix thickness was too thin for a cold in-place recycle and the amount of cracking in the existing plant mix could result in reflective cracking with an overlay.  Hot in-place recycle was the selected method and will provide more structure and less potential for reflective cracking than an overlay.

-7-
Submitted: Friday    19-OCT-2018 12:17 PM
Company: Schellinger Construction Company, Inc.
Contact: Estimating
Special Provision No.27 states MDT will take cores of the existing asphalt every 1 mile and a stripping analysis will be performed.  Will MDT please post the results of these test.
Answer
Submitted: Friday 19-OCT-2018 03:05 PM
Linked for information only is the Stripping Analysis Report:
  STRIPPING ANALYSIS REPORT

-8-
Submitted: Friday    19-OCT-2018 02:15 PM
Company: Helena Sand & Gravel
Contact: Estimating
Special Provision #27 references adding commercial plantmix to the Hot-in-Place-Recycle. The specification also states "add commercial plantmix as shown in the contract".
1)   Is commercial plant mix to be added to the HIR?
2)   If so, how much? and how is it paid?
Answer
Submitted: Wednesday 24-OCT-2018 08:55 AM
Special Provision #27. HOT IN-PLACE RECYCLE (HEATING AND REMIXING) Paragraph C. states; “If the addition of commercial plant mix is not specified in the contract, but is necessary to meet the mix design requirements, furnish the necessary mix with the Project Manager’s approval. If approved, commercial mix will be paid for in accordance with Subsection 109.04.” 

If the Contractors mix design requires Commercial Plant Mix, furnish Commercial Plant Mix with the Project Manager’s approval and, if approved, it will be paid in accordance with Subsection 109.04.

-9-
Submitted: Saturday  20-OCT-2018 09:56 AM  
Company: MWHC  
Contact: Chris Connors
There is a bid item for Poles-Treated Wood 5in but the signing summary does not show any to be done.  Additionally, the sign summaries included Posts Structural Steel but there is no bid item for that work.
Answer
Submitted: Monday 22-OCT-2018 11:08 AM
Signing Plan Sheets S1-S4 have been revised and are attached.
  SIGNING SHEETS S1-S4
An addendum will be issued to delete Bid Item 619 010 490 - POLES-TREATED WOOD 5 IN and add Bid Item 619 010 320 - POSTS - STRUCTURAL STEEL, Quantity - 208.00 LB