Skip to main content

Contract Information


Project Name BR PRES FLATHHEAD CR-N WILSALL
Advertise Date 09/27/2018 04:00 PM
Close Date 10/22/2018 10:00 AM
Let Date 10/25/2018 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

No clarifications found for this contract

Questions

-1-
Submitted: Monday    01-OCT-2018 09:58 PM  
Company: Diamond Drilling and Sawing Co.  
Contact: Eric Blackburn  
Requesting asbuilts of existing bridge.
Answer
Submitted: Tuesday    02-OCT-2018 10:46 AM
The files linked below represent the as-built drawings for the structures. MDT provides them for informational purposes only. They do not include drawings for modifications to the structures, such as joint replacements and guardrail revisions and may not completely represent current conditions. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents.
AS-BUILTS

-2-
Submitted: Friday    19-OCT-2018 11:42 AM
Company: COP Construction
Contact: Olivia Poettmann
Will stay in place forms be allowed for the bridge deck?
Answer
Submitted: Monday    22-OCT-2018 10:22 AM
Stay in place deck forms are not allowed.

-3-
Submitted: Friday    19-OCT-2018 03:55 PM
Company: Helena Sand & Gravel
Contact: Estimating
Item # 104 030 019 Reset Miscellaneous
Sheet 6 of the plans shows this as Emb Protectors. What work is required for this item?
Answer
Submitted: Tuesday    23-OCT-2018 04:11 PM
The intent is to remove the existing embankment protectors and reset them after the 30- year bridge end treatments are installed. Please reference Detailed Drawing 603-28 Embankment Protector for installation requirements.

-4-
Submitted: Sunday    21-OCT-2018 02:53 PM  
Company: MWHC  
Contact: Chris Connors
Plan page B2 has a note for the temporary barrier that says not to use type 2 or 3 anchors to attach the temporary barrier to the NEW DECK.  Is the intent of this note to use either type 2 or 3 anchors when placing on the old deck?
Answer
Submitted: Tuesday 23-OCT-2018 08:12 AM
The temporary concrete barrier rail used for phase 1 needs to limit deflection of the system, therefore type 2 or 3 anchors are required in the existing bridge deck. 
The temporary concrete barrier rail used for phase 2 does not need to limit deflection of the system, therefore do not use type 2 or 3 anchors in the new bridge deck.