-1-
Submitted: Thursday 06-DEC-2018 03:46 PM
An Addendum has been posted for this project: ADDENDUM
To download the addendum bid files, click here: BID FILES
NOTE: When loading the addendum, notes concerning General Changes may appear due to software updates and can be disregarded.
|
-2-
Submitted: Tuesday 11-DEC-2018 04:15 PM
Addendum No. 2 has been posted for this project: ADDENDUM NO. 2
To download the addendum bid files, click here: BID FILES
|
Clarifications
|
-1-
Submitted: Thursday 29-NOV-2018 04:21 PM
The following plan sheets have been revised.
Sht. No. 10 - Typical No 3 – The station callout on the tenth line has been corrected to 1334+10.00.
Sht. No. 12 - The Pulverization Frame has been revised with new quantities.
Sht. No. 13 – The Grading Frame has been revised with new quantities.
Sht. No. 25 – The first station callout was corrected to 1214+93.00.
Sht. No. 34 – The callout for the VPI at station 1254+20.00 was added.
The revisions to sheets 10, 25 & 34 did not result in any design or quantity changes, just text.
The quantity revisions shown on sheets 12 and 13 for Pavement Pulverization, Excavation-Unclassified
and Excavation-Unclassified Borrow will be updated by addendum.
The revised sheets can be found at the following link: REVISED PLAN SHEETS
|
Questions
|
-1-
Submitted: Monday 19-NOV-2018 07:46 PM
Company: Prince, Inc.
Contact: Mike Sharp
Is the pulverization quantity correct? There does not appear to be 48.3' of existing roadway to pulverize 1.2' deep. This also significantly impacts the grading quantities if it not correct.
Answer
Submitted: Wednesday 21-NOV-2018 03:17 PM
Pulverize to the depth shown in the plans. Blend the remaining existing material from the edge of oil to the subgrade with the pulverized material and spread to the grades shown in the plans.
An addendum will be created to change the pulverization frame to reflect pulverizing 28 ft top and 2 ft inslopes for a total of 32 ft. (191,759 yd2) and change the unclassified excavation and unclassified borrow quantitates to accurately reflect the in-place quantities.
|
|
-2-
Submitted: Monday 26-NOV-2018 07:55 AM
Company: Prince, Inc.
Contact: Mike Sharp
Please provide a clarification for your answer on the previous question. The volume of pulverized material available within the template has been reduced by roughly 40%. Is the intention to supplement the pulverized material with CAC (CAC leveling) in order to reach the grades identified within the plans or drop the grades by approximately 0.2' thus decreasing the pulverized sub-base depth to .34' (Typicals 3,4,&6) and .18'(Typical 5) or ???
Answer
Submitted: Wednesday 28-NOV-2018 08:37 AM
There will be enough pulverized material to accommodate the needs of the typical sections.
|
|
-3-
Submitted: Wednesday 28-NOV-2018 01:35 PM
Company: YEC LLC
Contact: Zac Mader
1) Can MDT please post the seed specifications and blanket specifications for the 610 100 560 RIPRAP REVEGETATION?
2) Can MDT add ECB High Performance to the Schedule of Items? It is called out in the plan summaries under the Permanent Erosion Control section (page 14).
3) Will MDT allow Flexamat to be used in place of rip-rap chutes?
Answer
Submitted: Thursday 29-NOV-2018 11:08 AM
1) The special provision for Riprap Revegetation is hereby added to the contract. RIPRAP REVEGETATION
2) An item for Erosion Control Blanket - High performance = 2,128 yd2 will be added by addendum.
3) Concrete Rolled Erosion Blanket is an acceptable substitution for the Type 4 Drainage Chutes. If a contractor elects to use this substitution, include all costs of furnishing and installation per manufacturers recommendation in the CUYD bid for Riprap-Class 2 Random.
|
|
-4-
Submitted: Thursday 29-NOV-2018 10:02 AM
Company: Nelcon Inc
Contact: Nelcon, Inc.
Per SP #32, can RAP materials be salvaged from the existing PTW?
Answer
Submitted: Friday 30-NOV-2018 02:06 PM
Rap material can be salvaged from areas (Typical 1 & 2) that are not being pulverized and used in the Typicals. Any RAP material that is used from the pulverization area (Typical 3-6) must be replaced with CAC at no cost.
|
|
-5-
Submitted: Friday 07-DEC-2018 08:06 AM
Company: Riverside Contracting, Inc.
Contact: Estimating
Please revise the dirt run and mass diagram to reflect the revised excavation and borrow quantities. Also, 140 working days is not enough time to complete a project of this magnitude, please add 20 working days to the contract.
Answer
Submitted: Tuesday 11-DEC-2018 04:06 PM
Contract time will be revised by addendum to 160 days. Special provision No 24, Sequence of Operations, Section B has been revised adding requirement no. 9) At least one lift of plant mix surfacing must be placed on the disturbed areas of the PTW prior to winter shutdown. Contract time will continue to be charged until this condition is met.
The Mass Diagram and Dirt Runs (Log file) has been updated and can be found at the following links:
UPDATED MASS DIAGRAM