Contract Information


Project Name WEST LAUREL INTCH-WEST PHASE 2
Advertise Date 01/24/2019 04:30 PM
Close Date 02/15/2019 03:00 PM
Let Date 02/21/2019 09:00 AM

Notifications

No notifications found for this contract

Addendums

-1-
Submitted: Friday    15-FEB-2019 04:22 PM  
An Addendum has been posted for this project: ADDENDUM
To download the addendum bid files, click here: BID FILES

Clarifications

-1-
Submitted: Friday    15-FEB-2019 03:52 PM  
The Public Approach surfacing shown in Typical Section No.17 has been revised to show 0.4’ of PMS, 1.1’ of Crushed Aggregate Course and 1.20’ of Special Borrow. Surfacing quantities will be updated by addendum.  Revised sheet #’s 14, 16 and S-13 can be found at the following link.  REVISED PLAN SHEETS 14, 16 & S13

-2-
Submitted: Wednesday    20-FEB-2019 12:45 PM
The following is hereby added to Special Provision 31. TRAFFIC CONTROL AND SEQUENCE OF OPERATIONS, Part D. Specific Requirements:
 - The intent of the four (4) 10-hour periods is to minimize two-way detoured traffic on ramps K1 and K2 and limit it to daylight hours.
 - The contractor may be allowed to temporarily detour eastbound traffic only onto ramps K1 and K2 while keeping westbound traffic in one of the existing eastbound lanes.  This would not count as one of the four periods allowed for a two-way detour on the ramps.  The same paving and guardrail requirements apply to the single lane ramp detour.  This will be considered on a case by case basis and requires approval by the Project Manager.
 - The requirements of Special Provision 56 WIDE LOAD ACCOMODATIONS apply to detour lane widths.

Questions

-1-
Submitted: Monday    04-FEB-2019 11:38 AM
Company: Knife River - Billings
Contact: Doug Teller
Can you please provide a link for the DGN CAD files and the Geopak files?
Answer
Submitted: Monday  04-FEB-2019 01:40 PM
The design files for the requested project are posted on the MDT FTP site for your use at:

West Laurel Interchange - West Phase 2 Design Files
The requested files do not represent the staked project, but are only design files.  The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents.
In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.

-2-
Submitted: Monday    11-FEB-2019 08:04 AM  
Company: SK Geotechnical  
Contact: Cory Rice  
Our firm performed the geotechnical work for this project. Will it be acceptable for us to quote the contractors for the dynamic load tests?
Answer
Submitted: Monday  11-FEB-2019 03:20 PM
It is acceptable for your firm to provide quotes to perform the dynamic load testing services on this project.

-3-
Submitted: Tuesday   12-FEB-2019 02:27 PM  
Company: Great Falls Fence  
Contact: Lee Carter
What are the specs on the galvanized steel panels mentioned in the remarks of the summary?
Answer
Submitted: Friday   15-FEB-2019 04:05 PM  
The galvanized steel panels are considered a special design.  As a result a Farm Fence Panels-Special Design Detail sheet has been added to the contract as well as new bid items for the Special Design panels.  These will be updated by addendum.  The revised plan sheets can be found at the following link: 
REVISED PLAN SHEETS 2, 15 & 25A

-4-
Submitted: Friday    15-FEB-2019 10:34 AM
Company: COP Construction
Contact: Olivia Poettmann
In the Special Provisions Item 9. Zone Pay states the millage to be used for determining the zone is 31 miles. Can you confirm the miles and the basis for determining this?
Answer
Submitted: Friday    15-FEB-2019 04:10 PM
The distance is 17 miles, rather than 31.  It is determined by measuring the road miles over the shortest practical maintained route from the County Courthouse in Billings to the center of the project.
For special provision No. 9, Zone Pay, the mileage is hereby revised to 17.

-5-
Submitted: Friday    15-FEB-2019 12:49 PM
Company: Knife River - Billings
Contact: Doug Teller
Are the millings generated from the Cold Milling item required to be hauled to a specific location for use by local municipalities, as is often the case?
Answer
Submitted: Friday    15-FEB-2019 04:15 PM
No.  Millings generated from the Cold Milling item will become property of the Contractor.

-6-
Submitted: Friday    15-FEB-2019 02:22 PM  
Company: Riverside Contracting, Inc.  
Contact: Estimating  
Will the contractor be able to use authorized vehicle median crossings or temporary median crossings outside the project limits? If so, how will the traffic control be paid?
Answer
Submitted: Wednesday    20-FEB-2019 11:53 AM  
Yes, the contractor will be allowed to use authorized vehicle median crossings or temporary median crossings for haul units in accordance with Section 618.03.7 of the contract.  Traffic Control will be paid in accordance with Sections 618.04 and 618.05.  Remove traffic control when the crossings are not in use.  Obtain an MDT Occupancy & Encroachment Permit for temporary median crossings and comply with all applicable environmental laws.  The contractor is responsible for any damage caused by haul units to existing authorized vehicle median crossings and for making associated repairs.