Contract Information
| Project Name | HYSHAM INTERCHANGE-EAST |
| Advertise Date | 02/28/2019 04:30 PM |
| Close Date | 03/25/2019 10:00 AM |
| Let Date | 03/28/2019 09:00 AM |
Notifications
No notifications found for this contract
Addendums
|
-1-
Submitted: Thursday 21-MAR-2019 04:08 PM
An Addendum has been posted for this project: ADDENDUM
To download the addendum bid files, click here: BID FILES
|
Clarifications
No clarifications found for this contract
Questions
|
-1-
Submitted: Tuesday 05-MAR-2019 10:08 AM
Company: Macon Supply
Contact: Jeff Monaco
Which bridge decks get a polymer overlay? The quantities on the bridge plans don't show a polymer overlay.
Answer
Submitted: Tuesday 12-MAR-2019 08:25 AM
None of the decks will receive a polymer overlay. The bid items for POLYMER OVERLAY and PREPARE DECK will be deleted from the contract. An addendum will be issued.
|
|
-2-
Submitted: Monday 18-MAR-2019 10:47 AM
Company: Alpine Sign, Inc
Contact: John
Special Provision 43 Wide Load Accommodations calls for Single Use Signs meeting ASTM Type IV or higher. I believe this should be Type VI or higher. Please clarify.
Answer
Submitted: Tuesday 19-MAR-2019 07:35 AM
Special Provision 43 Wide Load Accommodations is correct. Provide background for Single Use Signs meeting ASTM Type IV or higher.
|
|
-3-
Submitted: Monday 18-MAR-2019 04:02 PM
Company: Wickens Construction Inc.
Contact: Michael Lutes
1) What are the construction easements for the pipe encasement at station 448+35? The south side of the roadway appears to only have 30 ft of working room available.
2) Protecting the underside coating of the new pipe will be difficult as it will need to be dragged into the existing pipe. If dragged on wooden runners, will the runners be allowed to be left in place?
3) Cement Grout: Will class - “Controlled Low Strength Material” (CLSM) be allowed for encasement?
4) Culvert Liner: Will class - “General” concrete be allowable for the Culvert Liner?
5) Construction Joints: Are horizontal Construction Joints allowed in the Culvert Liner to facilitate 2 pours?
Answer
Submitted: Monday 25-MAR-2019 09:19 AM
1) The available right-of-way (measured from the median centerline) is 130 ft to the south side and 230 ft to the north side (approximate fence line).
2) If runners are left in-place, utilize steel runners and ensure grout fills all voids.
3) No, CLSM will not be allowed for encasement.
4) Yes, Class General Concrete will be allowed for the Culvert Liner.
5) Yes. However, joint must be sealed with a product approved by the Project Manager.
|