Contract Information


Project Name SF 129-SKID TREATMENT EAST MISSOULA
Advertise Date 02/28/2019 04:00 PM
Close Date 03/25/2019 10:00 AM
Let Date 03/28/2019 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

No clarifications found for this contract

Questions

-1-
Submitted: Wednesday 13-MAR-2019 10:03 AM 
Company: L & J Construction Group LLC 
Contact: Estimating
Will MDT consider moving the NTP to July 8th Flex Date? The strip seal steel joint takes at least 3 months to procure. The anticipated award is April 9th. 3-4 weeks for shop drawings. 3-4 weeks for MDT review of shop drawings. 4-6 weeks to manufacture and deliver. Installation of the strip seal is the critical path for the project.
Answer
Submitted: Friday 15-MAR-2019 01:56 PM 
Yes, MDT will modify the NTP and now allow a Flex NTP of July 8th.  Special Provision No. 2. Contract Time is hereby replaced with
CONTRACT TIME – FLEX TIME PROCEED DATE

-2-
Submitted: Friday    15-MAR-2019 12:21 PM  
Company: The D. S. Brown Company  
Contact: Melissa Good  
Could a cross-section showing slopes and curbs/barriers of each structure please be provided? It would be beneficial to provide a more accurate quote for the fabricated joints being replaced.
Answer
Submitted: Monday    18-MAR-2019 01:54 PM  
Cross sections of the bridge decks can be found in the as-built plans.  Note that the eastbound bridge deck has been replaced.
The files linked below represent the as-built drawings for the structures. MDT provides them for informational purposes only. They do not include drawings for modifications to the structures, such as joint replacements and guardrail revisions and may not completely represent current conditions. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents. 
AS-BUILTS