|
-2-
Submitted: Wednesday 13-MAR-2019 11:56 AM
Special Provision No. 2, CONTRACT TIME is hereby replaced with the linked Special Provision No. 2, CONTRACT TIME – CALENDAR DAY.
2. CONTRACT TIME - CALENDAR DAY [108] (REVISED 1-21-16)
This contract is a calendar day contract. The work begins on the effective date stated in the Notice to Proceed (NTP) and all work is to be completed in 50 Calendar Days. Unusually severe weather is not considered as a delay cause. The NTP will be issued with an effective date of May 28, 2019.
In addition, Special Provision No. 15, TRAFFIC CONTROL & SEQUENCE OF OPERATIONS, Paragraph E. (2nd Paragraph of E.) is hereby replaced with the following:
Maintain a minimum of one-way traffic at all times on Collins Road. Maintain access to
and from the premises of adjacent property owners at all times. Keep open all intersecting
roadways, all public and private drives and entrances at all times by temporary measures
except for the time required for providing these temporary measures. The southbound lanes of
I-15 may be shut down for 50 calendar days with the use of the off-ramps as the temporary
detour of southbound traffic. Roadway closures will not be allowed during the winter shutdown
period from November 16th through April 15th. Maintain at least one 12-foot lane of traffic at all
times on Collins Road . Night work is allowed. Notify the Project Manager a minimum of five (5)
calendar days prior to performing night work.
An addendum and amendment bid file will tentatively be issued on Thursday, March 21, 2019 formalizing the above clarification.
|