|
-1-
Submitted: Monday 11-MAR-2019 05:07 PM
Company: WGM Group
Contact: Cody Thorson
With resumes counting as page limits, and the staffing plan of the SOQ being counted with the Technical Proposal scoring, can the page limit of the SOQ be increased to 40 pages?
Answer
Submitted: Tuesday 12-MAR-2019 08:15 AM
Five (5) additional pages is added to the Statement of Qualifications page limit for a total page limit of 35 pages allowed.
|
|
-2-
Submitted: Wednesday 13-MAR-2019 12:39 PM
Company: WGM Group
Contact: Cody Thorson
The RFQ states that initial survey data by MDT will be attached to the RFP. Can MDT please post this data including any Microstation files.
Answer
Submitted: Wednesday 13-MAR-2019 01:39 PM
SURVEY FILES
The preliminary survey files are now available in the Q&A forum. We recommend caution when using these files as the information is dated and may not provide complete project coverage. The Design-Build Firms’ herewith accept responsibility for the accuracy and completeness of the data. The design files for the requested project are posted on the MDT FTP site for your use at:
The requested files do not represent the staked project, but are only design files. The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents. In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.
|
|
-3-
Submitted: Thursday 21-MAR-2019 11:15 AM
Company: WGM Group
Contact: Cody Thorson
The survey files posted on the Q and A reference DIMAPs, specifically 8914000DIMAP001.dgn and 8914000DIMAP002.dgn. These files, along with 8914000SACMA001.dgn were not included in the posted information. Can MDT provide these files?
Answer
Submitted: Friday 22-MAR-2019 08:58 AM
The preliminary survey files are now available in the Q&A forum. We recommend caution when using these files as the information is dated and may not provide complete project coverage. The Design-Build Firms’ herewith accept responsibility for the accuracy and completeness of the data. SUPPLEMENTAL SURVEY
|
|
-4-
Submitted: Thursday 21-MAR-2019 01:45 PM
Company: Schellinger Construction Company, Inc.
Contact: Mark Cyr
After reviewing the RFQ, our Engineering and Design firm decided to pull support for this project. This was due to the number of high-risk elements and the amount of risk that will be placed on the Design Build Team. We are still very interested in this project and have been actively pursuing a new firm. We have located a new firm that has agreed to team with us, if we can get an extension on the due date for the SOQ. Given these unfortunate circumstances were beyond our control, would MDT consider moving the SOQ response due date out to April 11, 2019?
Answer
Submitted: Thursday 21-MAR-2019 04:27 PM
Due to internal scheduling restrictions we are unable to reschedule the SOQ due date for this project.
|
|
-5-
Submitted: Wednesday 17-APR-2019 09:52 AM
Company: WGM Group
Contact: Cody Thorson
The Preliminary Geotechnical Evaluation report included in the SOQ documents, section 4.0, references geotechnical borings scheduled to be completed in February 2016. Was this drilling performed, and if so can the information be provided?
Answer
Submitted: Wednesday 17-APR-2019 11:53 AM
A comprehensive geotechnical investigation has not been performed, however some preliminary subsurface information has been obtained. This information is provided at the following link: SOIL SURVEY DATA
Attached are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.).
|
|
-6-
Submitted: Tuesday 23-APR-2019 12:25 PM
Company: WGM Group
Contact: Cody Thorson
Can MDT post the available crash data, including location and type of crashes, for the project corridor?
Answer
Submitted: Friday 26-APR-2019 11:44 AM
Crash data has been sent to the three short listed firms.
|
|
-7-
Submitted: Wednesday 24-APR-2019 10:31 AM
Company: WGM Group
Contact: Cody Thorson
Are teams allowed to contact adjacent landowners along the project corridor, that will likely have R/W impacts, prior to project Award?
Answer
Submitted: Wednesday 24-APR-2019 13:49 PM
MDT requests that the firms refrain from contacting landowners and the general public prior to the award of the project.
|
|
-8-
Submitted: Wednesday 08-MAY-2019 07:02 AM
Company: KLJ
Contact: TRAVIS WIEBER
Can copies of the encroachment permits for known utilities be made available?
Answer
MDT will provide electronic copies of the utility occupancy permits along the project limits. Note that there is the possibility that the utilities may have been upgraded and/or relocated. Use caution when referencing this information.
|
|
-9-
Submitted: Wednesday 08-MAY-2019 07:01 AM
Company: KLJ
Contact: TRAVIS WIEBER
What timeline can be assumed for final environmental approval once the draft environmental document has been submitted to MDT?
Answer
Submitted: Wednesday 08-MAY-2019 09:54 AM
Assuming that the draft environmental document submitted to MDT by the Firm is complete and addresses all of the appropriate items, it takes 14-calendar days for MDT internal review/approval and then approximately 30-calendar days to obtain signatures and FHWA approval. Note that if the draft document is inadequate, additional time will be required for the Firm's revisions and MDT's internal re-review of the document.
|
|
-10-
Submitted: Friday 10-MAY-2019 02:36 PM
Company: KLJ
Contact: TRAVIS WIEBER
As per 9.2.1.5 of the Road Design Manual, "For paved roads, utilities should be located outside the clear zone, but no less than 30 feet from the edge of the outermost lane." There are several utilities, specifically fiber optic lines, that will fall within the clear zone but would not necessarily be impacted. Is it MDT's intent to relocate any and all utilities, regardless of impact, that fall within the roadway clear zone?
Answer
Submitted: Monday 13-MAY-2019 09:22 AM
Any above ground utility located in the clear zone that represents a hazard to motorists must be relocated out of the clear zone. MDT does not require unimpacted utilities to be relocated.
|
|
-11-
Submitted: Saturday 11-MAY-2019 06:28 PM
Company: WGM Group
Contact: Cody Thorson
Can MDT provide direction on permanent fence requirements? Is the intent to fence only properties that are currently fenced, or to fence all right-of-way?
Answer
Submitted: Monday 13-MAY-2019 12:54 PM
In accordance with MDT's R/W policy, we only require replacing existing fencing, in kind. The design-build firms will need to assess existing fencing and make their best estimate on the type and cost of the fence replacements. Any upgrades from the firm's design that is agreed to during R/W Acquisition will be the responsibility of the Firm and no additional payment will be made by the Department. The Firm should consider the risk of this potential situation and bid the project accordingly.
|
|
-12-
Submitted: Friday 24-MAY-2019 10:48 AM
Company: KLJ
Contact: TRAVIS WIEBER
During our team's utility investigation, we learned that approximately 10,000 feet of fiber optic line will be installed along the corridor in the summer of 2019. Will the proposers be responsible for relocation costs of new utilities that are not currently in place and therefore cannot be quantified or priced?
Answer
Submitted: Tuesday 25-MAY-2019 04:36 PM
The design-build firm will not be responsible for the cost to protect or relocate utilities built after this project is awarded. MDT will work with the design-build firm and the appropriate utility company to attempt to mitigate potential impacts of the project on the described new utilities.
|
|
-13-
Submitted: Monday 27-MAY-2019 09:53 PM
Company: WGM Group
Contact: Cody Thorson
Should the following paragraph of the RFP be deleted? If not, please clarify this requirement. Part III. Threshold Requirements, Paragraph L. (bottom of page 14) "MDT makes no guarantee the Firm will receive the total quantities shown in the RFP for each location. The quantities are shown for information only to provide a consistent bid quantity to all Firms during the Bid Price Proposal phase. The actual quantities measured during construction will be paid. The unit prices indicated by the Firms in the Bid Price Proposal will be used in the event the quantities stated in the Firms preliminary design overrun or under run in accordance with Standard Specification 104.02. If the quantities change for only a portion of the elements included in the lineal foot cost, MDT and the Firm will negotiate a unit price based on the elements changed."
Answer
Submitted: Tuesday 28-MAY-2019 08:14 AM
The described paragraph located in Section III, Part L is deleted from the RFP.
|
|
-14-
Submitted: Wednesday 29-MAY-2019 07:25 AM
Company: WGM Group
Contact: Cody Thorson
The list of anticipated design plans under Section VI, Paragraph B (page 26 of the RFP) does not include cross sections. Will cross sections be required with the plan sheet submittals?
Answer
Cross sections developed in accordance with Section 12.3.12.1 General Considerations of the Road Design Manual will be required with the design submittals for this project.
|
|
-15-
Submitted: Wednesday 29-MAY-2019 08:51 AM
Company: WGM Group
Contact: Cody Thorson
The Federal Wage Rates provided in the RFP appear to be incorrect (Building Construction Projects - Carbon Cty). Can MDT post the applicable wage rates for this project?
Answer
Submitted: Wednesday 29-MAY-2019 11:47 AM
The Attachment G -Contract Backs which include the federal wage rates posted in the RFP are not correct. For this project reference the revised Contract Backs which include the appropriate Highway wage rates at the following link: CONTRACT BACKS
|