Contract Information
| Project Name | TERRY-FALLON AREA NHS BRIDGES |
| Advertise Date | 03/14/2019 05:00 PM |
| Close Date | 04/08/2019 10:00 AM |
| Let Date | 04/11/2019 09:00 AM |
Notifications
No notifications found for this contract
Addendums
No addendums found for this contract
Clarifications
No clarifications found for this contract
Questions
|
-1-
Submitted: Wednesday 03-APR-2019 07:48 AM
Company: Mountain West Holding Company
Contact: Keith Johnston
1) Will the contractor have to accommodate wide loads during construction? If so would it be the typical two hours per day four days per week?
2) Also, if wide loads must be escorted though the project there will be a need for single use signs. Can a bid item be added for single use signs or could the MDT provide sign design calculations for the signs that will be required.
Answer
Submitted: Wednesday 10-APR-2019 08:35 AM
The contractor will not need to provide wide load staging on this project, but may need to coordinate wide loads through the project. The tentative plan is to have a 16 ft width restriction in place while traffic is on the crossovers.
|