Project Name DRAINAGE - 6 MILES EAST GLENDIVE
Advertise Date 03/28/2019 04:30 PM
Close Date 04/22/2019 10:00 AM
Let Date 04/25/2019 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

-1-
Submitted: Monday  22-APR-2019 12:07 PM
The supplemental specification for Subsection 104.02.3 Significant Changes in the Character of Work incorrectly refers to Subsection 104.03.2. Both occurrences of 104.03.2 are hereby changed to 104.02.3.

Questions

-1-
Submitted: Thursday  11-APR-2019 12:59 PM
Company: Battle Ridge Builders, LLC
Contact: Cody Ham
The existing bridge needs to be de-nested and bird deterrents installed on or by next Monday to comply with the migratory bird provisions if we want to start this project before August 1st, is this something the State can do? Otherwise it doesn't seem like the flex date doesn't apply.
Answer
Submitted: Monday  15-APR-2019 09:30 AM
This project doesn't require the Migratory Bird Treaty Act special provision.

-2-
Submitted: Thursday  11-APR-2019 01:00 PM
Company: Battle Ridge Builders, LLC
Contact: Cody Ham
Just to confirm, is a SPA124 permit for temporary facilities necessary for the detour installation?
Answer
Submitted: Friday  12-APR-2019 01:20 PM
Yes, a temporary facility SPA-124 permit will be required to construct the detour. The SPA authorization (MDT-R7-31-2018) mentioned in Special Provision 11 only authorizes the permanent features. See Standard Specification 208.03.3 B regarding temporary facilities and construction activities. Also see Special Provision 13 regarding 404 temporary facility permitting, which is also required.

-3-
Submitted: Wednesday 17-APR-2019 07:39 AM 
Company: MWHC 
Contact: Chris Connors
Special Provision #20 Sequence of Operations states that the detour is to be a single lane and to install the appropriate traffic control measures to ensure safe operation. Is it the Departments intent to use temporary traffic signals to accomplish this? The geometry and length of the detour combined with staged equipment may make it difficult for traffic to have a clear view of oncoming traffic from the opposite direction.
Answer
Submitted: Thursday 18-APR-2019 01:07 PM 
Temporary Traffic Signals or flaggers would be acceptable for this detour.

-4-
Submitted: Monday    22-APR-2019 09:25 AM
Company: Forterra
Contact: Jared Masin
The Pre-cast 15'x8' double cell box is going to weight around 61,000 lbs a section. Is it possible to use two 15'x8' boxes side-by-side instead of one double cell box, to save on weight of each section?
Answer
Submitted: Wednesday    24-APR-2019 09:09 AM
Yes, two 15'x8' boxes side-by-side may be used.  Bid item will remain as Reinforced Concrete Box 15 x 8 dbl. - 87.00 LNFT.