Skip to main content

Contract Information


Project Name KILA - E & W (2 TIED PROJECTS)
Advertise Date 05/16/2019 04:30 PM
Close Date 06/10/2019 10:00 AM
Let Date 06/13/2019 09:00 AM

Notifications

No notifications found for this contract

Addendums

No addendums found for this contract

Clarifications

-1-
Submitted: Wednesday  22-MAY-2019 09:39 AM
REVISED: Thursday  23-MAY-2019 01:05 PM
Due to Cold Millings disposal locations changing in Flathead County, special provision #33, Recycling and Disposal of Cold Millings is hereby replaced and can be found at the following link:  RECYCLING AND DISPOSAL OF COLD MILLNGS REVISED
The above linked special has been updated regarding the application of RAP.  The 2nd sentence of Section B is revised to say “If used, the application of recycled asphalt pavement must be performed in accordance with Supplemental Specification 401.02.5.”

Questions