Contract Information
                  PLAINS - S OF HOT SPRINGS AND PLAINS - NW - JULY 23, 2015 LETTING
                
              
                  06/25/2015 05:00 PM
                
              
                  07/20/2015 10:00 AM
                
              
                  07/23/2015 09:00 AM
                
              Notifications
                        No notifications found for this contract
                        
                      
                    Amendments
                    No Amendments found for this contract
                    
                  
                Clarifications
| -1- Submitted: Mon, 06-Jul-2015 16:35 MDT Special Provision #2 – Contract Time – Flex Time Proceed Date is hereby revised as follows – replace B. Notice to Proceed with the following: B. Notice to Proceed. The notice to proceed will be issued with an effective date of November 16, 2015. The Contractor may change the notice to proceed date to an earlier date if written notification is received at least ten calendar days in advance of the date selected and the selected date is approved by the Project Manager. Include an updated schedule with the notification.  | 
                      
Questions
| -1- Submitted: Tue, 30-Jun-2015 19:18 MDT Company: Schellinger Construction Co., Inc. Contact: Marc Blanden Is there a mandatory pre-bid meeting for this project? Submitted: Wed, 01-Jul-2015 08:21 MDT There is not a mandatory pre-bid meeting for this project.  | 
                      
-2-  | 
                      
| -3- Submitted: Tue, 14-JUL-2015 04:15 PM Company: Schellinger Construction Co., Inc. Contact: Marc Blanden Section IV. C.1.a of the MOU states "For any project that MDT is constructing on the Reservation, MDT and the Tribes will consult to identify and select the source and location for temporary withdrawal of water for construction puposes." Is there a water source available and what is the location of this source? Submitted Thu, 16-Jul-2015 08:15 MDT MDT did not establish any water sources with the Tribes. According to the PSA for this project, "Water to be used by the contractor for the Project may be obtained by the prime contractor from any lawful source desired by it. There will be no Tribal charges to the contractor for Project water unless the prime contractor negotiates and obtains water from a tribally-owned source."  | 
                      
| -4- Submitted: Tue, 14-JUL-2015 05:09 PM Company: Schellinger Construction Co., Inc. Contact: Marc Blanden 1. The MOU Part G.2.Tero Fee: states "For projects that are located only parly on the Reservation, the TERO fee assessment will be pro-rated to be equivalent to the ratio of miles of project within the Reservation to total miles of the project." Can MDT provide a percentage of the total contract amount that the TERO Fee will be applied too? 2. The PSA Part D. states "An Indian Preference Contracting Fee ("IPC fee") of three percent (3.0%) will be assessed against the total contract cost." Is the IPC Fee the same as the TERO fee? or is this an additional fee? Is the IPC Fee charged on the total contract or a percentage as stated in the MOU? 3. Additionally there is no mention of an Improvement of Services (IOS)fee in the PSA. Is there no required IOS fee on this project? Submitted: Tuesday, 21-JUL-2015 12:45 PM 1. The TERO Fee will be prorated based on 54.14% of the total project located on the reservation. 2. The IPC fee is the same as TERO. The IPC fee is based on the percentage of the contract located on the reservation. 3. There is not an IOS fee on this contract.  |